The William H. Rumsey Aquatic Center will close Oct. 1, 2026, clearing the way for demolition and construction of a $44.5 million replacement beside Eastern Market.
The DC Department of Parks and Recreation (DPR) and Department of General Services (DGS) will hold another community meeting Tuesday, Sept. 22, from 6:30 to 8 p.m. in the North Hall of Eastern Market (225 Seventh St. SE). The meeting is expected to provide a construction schedule and an opportunity for residents to learn whether the agencies changed plans in response to comments submitted after the July design presentation.
The closure date is a major update. At the July 22 meeting, officials said they would not take Rumsey offline until construction was ready to proceed and promised substantial notice, but they had not identified a date for closure or demolition. DGS continues to list completion for early 2028.
The District plans to demolish the 1970 building at 635 North Carolina Ave. SE and replace it with a two-story community and aquatic center. Plans presented in July include an eight-lane, 25-yard lap pool with depths from four to 12 feet and a separate 40-by-34-foot leisure and learn-to-swim pool descending from three and a half to five feet. The building would also include locker rooms, family changing rooms, a sauna, a fitness room, senior space, meeting rooms and an observation area overlooking the pools.
The September meeting follows unresolved comments from some of Rumsey’s most regular users in July. Water aerobics participants said a four-foot shallow end would be too deep for many shorter adults and would leave too little standing room for large classes. Christopher Dyer, DPR’s community engagement manager, called a request to begin the lap pool at three and a half feet “an easy fix,” but the project team did not commit to it.
Water walkers raised the opposite concern. They said the five-foot maximum in the smaller pool would be too shallow for many participants to exercise without touching the bottom. That could force the program back into the lap pool and renew competition for lanes. Officials said DPR aquatics staff still had to determine pool capacities and program scheduling.
It is not yet clear whether the depths have changed, how the two pools will be divided among lap swimming, lessons, water aerobics and water walking, or whether DPR has identified alternative locations and schedules for programs during the closure. Residents also asked for more showers and changing space, suit-spinning machines, recessed ladders and additional deck hooks.
Construction impacts remain another question. Eastern Market representatives asked the agencies to protect merchant access and income, provide electrical service for vendor tents, maintain alley lighting and coordinate security. The project team said the construction fence would leave the residential alley open, but details about staging, truck routes and effects on market operations were not settled publicly in July.
DGS says the project will preserve the plaza and heritage tree along North Carolina Avenue, retain existing parking and the Capital Bikeshare station, and add bicycle racks. The design also includes wider sidewalks, stormwater planters, solar panels and a green roof. The agencies have said broader analysis of traffic, street parking and bus service falls outside the project’s scope.
The Sept. 22 meeting should show which community requests made it into the construction documents and give swimmers their first clear picture of where programs will go after Oct. 1. Project information and earlier presentations are available on the DGS Rumsey Aquatic Center webpage.