Here’s an update on big DC Department of Parks and Recreation (DPR) construction projects in the District. We’re going to offer it in two parts, the first today (Wednesday) and the second Aug. 1, because there are 12 DPR capital projects that impact our readers on the Hill and adjacent neighborhoods.
In late July, members of the DPR planning and design team, led by DPR Community Planner Nick Kushner and Capital Projects and Design Manager Brent Sisco, provided an update on projects of interest to residents at two meetings last week.
The meetings were organized by ward. The meeting concerning Ward 7 Capital Projects took place July 23, and the Ward 6 Capital Projects Update took place July 29.
Capital projects are long term, larger scale investments that improve, add to or create a property. They have a higher budget and are managed in the District by the Department of General Services (DGS) the District’s construction and maintenance arm.
There are 10 projects specific to Ward 6 and two more in Ward 7 on the Hill. Here updates on the six that are complete or are furthest along. Today we’ll look at the status of improvements to Spielberg Park, the Eighth Street Triangle Park, Cobb Park, Garfield Park, the exterior of Sherwood Recreation Center and at the Kingsman Field and Dog Park.
Tomorrow: we turn to updates on work that is a bit less progress on their timelines. Thursday, we look at Watkins Field and playground, the fields at Jefferson Middle School Academy, the Southwest Town Center Park, and the status of planned renovations to Rosedale Pool, Randell Recreation Center and at Rumsey Aquatic Center.
Project Updates

- E Street and Massachusetts Avenue Triangle Park. Refurbished this year at a cost of $615,000. DPR Community Planner Nick Kushner said the park was in disrepair with a water feature at center that no longer worked. The community demanded a refurbishment of the space. Work included improvement of aesthetics and landscaping, new furnishings, notably the cured benches at center, some ADA improvements and repairs to retaining walls. A new path provides entry from Constitution Avenue NE. [see our June story here].

From DPR Ward 7 presentation July 23. Screenshot Youtube: DC Department of Parks and Recreaton - 17th and C Street SE Triangle (Spielberg) Park. A $750,000 renovation of the park across from the row of houses used by Steven Spielberg in the filming of Minority Report (2002). To compensate the neighborhood, Spielberg installed new playground equipment. 22 years later, DPR replaced the playground equipment, saying it was getting to be a bit dangerous, provided drinking fountains, benches, tables, turf, landscaping and water fountains.
“This was a small project but these small projects are really important as they are Community Resources,” Sisco said at the Ward 7 meeting. Spielberg Park was also the site of a testing project; kids in each community come out and look at playgrounds before they open and use the equipment, Sisco said. “They play around they give us their opinions so we are we’re hearing from the users up front —what they like and what they don’t like and that’s honestly really helping us move forward because we are taking notes from the from the experts when it comes to playground equipment and that’s been a huge success.”
- Garfield Park (Third Street at South Carolina Avenue SE). “We’re right around the corner from mobilization,” Kushner said, adding that they were only waiting for one more document. The space will be refurbished, adding elements the community has requested for some time. New and refurbished playground equipment, lighting and landscaping, ADA improvements. The community will be notified when shovels are in the ground, presumably in late July or early August and will be wrapped up in late fall or early winter —after 2 to 6 months.
Kushner acknowledged that maintenance of the park is uppermost in the minds of the community after a falling tree killed Sarah Noah in the park July 10. “I know our hearts go out to [those suffering from] the horrible tragedy in the park the other week,” Kushner said.
- Cobb Park (200 H St. NW). The $2.1 million renovation of this park, located above the i-395 between Massachusetts Avenue and H Street NW is currently in permitting, with a few things to be signed off on; Kushner said neighbors should see movement in the late summer or early fall.The fenced-off green space at Second and H Street NW will be turned into an attractive green space with a play area for kids, a plaza, water fountains and lighting around an open lawn —the Mount Vernon SID is thinking of programming the space, Kushner said. There will also be an elevated berm for relaxing. Work is expected to be begin later this summer or fall, after the completion of work on the 395 tunnel beneath, currently underway.

From DPR Ward 6 presentation July 29. Screenshot Youtube: DC Department of Parks and Recreaton - Sherwood Recreation Center (640 Tenth St. NE) Sisco acknowledged the work of ANC 6A03 Commissioner Roberta Shapiro, a huge advocate for the $1.3 million project making outdoor improvements to the Northeast recreation center.Both the basketball and tennis courts will be renovated, and the water fountain will be replaced. “there is a huge problem with I think children putting things in the water fountain —of course that’s what we, that’s what kids do— and you know we have evolved over time to have newer water fountains that do much better with not getting clogged,” Sisco noted. But the biggest change will be with the outdoor oval field.
Now filling in with grass and peppered with holes, it will become a synthetic turf inside of a walking track. The court work will begin prior to that oval field work, Sisco said, but permits are taking longer than anticipated. Construction was planned to begin in late fall, lasting 3 to 5 months, into winter of 2025, weather permitting.

- Kingsman Field and Dog Park Upgrade (D Street at Tennesee Avenue NE). Budgeted for $1.25 million, this project includes a full renovation of the existing dog park, upgrades to the basketball court, minor improvements to the fencing around the field and upgrades to the water fountain. “I know there have been standing water issues in this park for years,” Capital Projects and Design Manager Brent Sisco said.
The Kingsman Bark organization worked with the DPR team to select engineered wood fiber surfacing for the dog park, “which is actually a new surfacing type which seems to be a better and easier on dog paws than the old stone dust that we typically used to use,” Sisco said. Construction is anticipated to begin in Fall 2024 and take about 6 months, ending in Spring 2025.
DPR Director Thennie Freeman reminded attendees at the Ward 6 meeting that budgets are usually created at the outset of a project. But three to five years can elapse from the design stage to when shovels hit the ground on a project. “There’s a saying that says yesterday’s prices are not today’s prices,” she said, explaining that allocated budgets may not retain the purchasing power expected.
DPR project update meetings are expected to take place quarterly, Sisco said, meaning if information changes DPR will be able to give updates at the next meeting. “This is really an effort on on dpr’s part to be proactive and and to meet folks in the communities or at least give you proactive updates on what’s going on in projects in your community,” Sisco said.
Freeman was appointed Interim Director of Parks and Recreation in April 2023, coming from the DC Department of Employment Services (DOES). The quarterly updates by ward are an innovation since she was confirmed in December.
You can watch the ward-by-ward construction updates online at https://https://wardupdates.splashthat.com/
Information for all DC Capital projects can be found at https://dgs.dc.gov/page/dgs-capital-constructionprojects.